Supplying and installing electrical and mechanical
equipment for AlHasakeh water project (second stage).
For the Public establishment of water supply
and sewage
Alhasakeh pumping
Station:

Horizontal pumping set: each 825 m3/h,Qty /10/, with
a complete set of accessories and electrical panels.

Transforming center 20 KVA/0,4 KV,medium voltage panels
for inlet and low voltage panels for outlet.

Gensets, each 850 KVA with its electrical panels.

Water Hammer protection system.
Alhasakeh sedimentation Station:

Washing pumps, washing air blowers for the
sand filters with all its accessories.

Sterilization pumps with the required chemical
materials and mixers.

Chlorine equipment with chlorine gas cylinders.

Gensets 200 KVA

Electrical bridge cranes

in different capacities for both of the stations.
Supplying and installing
electrical and mechanical equipment for extending
Tal Tamr water projects and its villages.
For the Public
Establishment of water supply and sewage-Alhasakeh.

Washing pumps, washing air blowers for the
sand filters with all its accessories and panels for
automatic washing system.

Sterilization pumps with the required chemical
materials and mixers.

Chlorine equipment.

Gensets with its accessories.

Electrical panels.
Supplying, installing and testing electrical and mechanical
equipments for Al-Ghamr irrigation project in Maskaneh.
For the Public
Establishment of water supply and sewage-Aleppo.
The purpose from this project is to pump tens of villages
immersed in Euphrates

Pumping sets 250m3/h, Qty/8/, with its accessories
and electrical panels

Gensets 850 KVA, 400V with the electrical
panels.

Compressed sand filters, Qty /10/ with the
accessories and automatic washing program.

Water hammer protection system.
Supplying,installing and testing electrical and mechanical
equipments for Sheikh Najjar 1 water project.
For Public Establishment
of water supply and sewage-Aleppo.

Centrifugal pump, Qty /2/, each 2500 m3/h
at 96m to feed the industrial section task in Sheikh
Najjar-Aleppo.

Medium voltage Gensets 2000 KVA with the accessories.

Medium voltage panels 6.3 KV for pumping and
generating sections for the electrical current feedinginlets
and for the pumps operating section.

Automation SCADA system to control the pumps
work and to transmit the signals to the computer.

Water hammer Protection system
Supplying,installing electrical and mechanical equipment
with the apandant civil works for the intake pumping
station in the Industrial city, Sheikh Najjar.
For Public Establishment
of water supply and sewage-Aleppo.

Multistage horizontal pumping sets, each 520
m3/h, Qty/4/ with the accessories and the electrical
panels

Water Hammer protection system.

Watering works for Ezaz and Efreen from 17
Nisan dam (sand filtration building), civil works
with supplying, installing and testing electrical
and mechanical equipments.
For Public Establishment of water supply and
sewage-Aleppo.

Mechanical equipment (washing pumps - air
blowers) with all its accessories of valves, gauges….etc
for the sand filters at the watering filtration station
in Ezaz and Efreen

Supplying, installing and testing the electrical
panels (distribution – Washing automated filters)
with all the accessories.
Supplying, installing and testing technical and mechanical
equipment, T.M.K. the first and second reservoir in
the motors hall of the upper station in the industrial
city, Sheikh Najjar.
For Public Establishment
of water supply and sewage-Aleppo.

Horizontal pumping sets, each 275 m3/h to feed
the first reservoir.

Horizontal pumping sets, each 190 m3/h to
feed the second and third reservoirs.

Automation system to control this station
with the intake station.

Water hammer protection system.

Replacing the pumping set of the second project
and its accessories with importing medium voltage
cables.
For Public Establishment of water supply and
sewage-Aleppo.

Horizontal pumping set, each 2500 m3/h at 96m
with all its accessories of valves, gauges and pipes.

Medium voltage panels to start and stop.

Temporary control panels using SCADA system
to transmit the information to the PC.

Electrical cables 6.3 KV in big quantities.

Water hammer protection system
Supplying and installing electrical and mechanical
equipment for Basel Al-Asad Martyr Station in Deir
Ezzor –second station.
For Public Establishment
of water supply and sewage-Deir Ezzor.
Water Intake Pumping
Station

Vertical pumping sets, each 900 m3/h with all
the accessories and electrical panels.

Horizontal pumping sets, each 846 m3/h with
all the accessories and electrical panels.
Sedimentation Station:

Washing pumps and washing air blowers for sand
filters with all its accessories and automatic washing
panels.

Sterilization pumps with the required chemical
materials and mixers.

Chlorine equipment with its accessories.

Ductile cast iron pipes DN800 mm
Supplying mechanical and electrical equipment for
the main pumping station and the subsidiary transforming
station in Albalikh basin.
For General Company
for Hydro-projects .

Vertical pumping sets, each 3.4 m3/sec with
all its accessories.

Medium voltage panels for distribution and
operation.

Automation and control panels.

Bridge cranes in different capacities.
Supplying and installing electrical and mechanical
equipment for Al-Maydin new plant.
For Public Establishment
of water supply and sewage-Deir Ezzor.

Manual and pneumatic valves in big quantities,
with blowers, water pumping sets, Sterilization station
using Sulphate aluminum, active carbon solution and
Poly electrolid solution.

Pumps, mixers and chlorine equipment with all
the accessories, electrical cranes and ultrasonic
flow meters. Electrical panels in different powers.

Outdoor lighting

Columns with its accessories.
|